Hospitality

Subway Drive-Thru Restaurant

Client

Kirk Bryson & Co

Duration

5 Months

project value range

Below £1m

location

Boucher Road, Belfast

Design team:

architect

Coogan & Co Architects

Structural

RPS Group

civil

RPS Group

M&E Services

F M Stewart & Associates

Quantity Surveyor

Terry Doherty Partnership

Procurement Route

Traditional

Role of MSM Contracts

Main Contractor

MSM were awarded this contract to construct a new single-storey Subway drive-thru shell restaurant unit including site development works (external works & drainage). The building fit-out was completed under a separate fit-out contract.

The works were located on a vacant site off Boucher Road, to the rear of a KFC drive-thru restaurant which continued trading throughout the 5-month construction period.

Key elements of the works involved:

– breaking up existing surfaces; removal of existing services

– constructing a 900mm re-aligned storm sewer & precast concrete headwall discharging into an adjacent watercourse

– mini-piling operations following confirmation of existing storm drain location

– RC pilecaps & ground beams; RC suspended ground floor slab

– structural steel frame; precast concrete units to lower roof

– superstructure masonry infill walling

– Kingspan KS500 ZIP Kingzip standing seam roof incl. flashings; Trocal

– Kingspan Micro-Rib wall cladding

– PPC aluminium wall cladding to feature wall & feature fin wall

– PPC aluminium curtain walling, windows & doors

– 100mm fast drying screed

External works involved:

– incoming mains utilities & site services; underground foul & storm drainage; site preparation incl. hardcore filling, geotextile membrane & kerbing; drive-thru associated works; surfacing & paving; fencing; external furniture