Building and Civil Engineering Contractors

Fast-track hotel project successfully delivered by MSM

MSM Contracts recently completed a fast-track construction project at The Belmont Hotel in Banbridge, Co Down. The construction works were carried out within a 6-week timeframe with The Belmont Hotel remaining open to guests at all times and involved alterations/extension works to construct a new night club entrance lobby and outdoor smoking area.

 

The project was handed over ahead of the XS Night Club & Entertainment Complex opening night on 05th December 2015 and enabled The Belmont Hotel to fully host their Christmas 2015 entertainment programme.

 

Site clearance and minor demolition works to an existing outdoor area and rear entry to the night club, were carried out during the enabling works phase. The newly formed night club entrance lobby is constructed with substructure blockwork on traditional pad & strip foundations, a structural steel frame with masonry infill walling and precast floor slabs. The building envelope combines roof cladding, PPC aluminium glazing and a smooth render finish. The night club entrance lobby was fully fitted-out by specialist contractors including M&E subcontractors, with bespoke finishes including custom-made floor coverings and a padded upholstery finish to the entrance doors and lobby desk.

 

External works involved laying decorative paving to the night club entrance and outdoor smoking area, perimeter fencing, landscaping and works associated with connections to the existing drainage system.

 

The design team on the project were Rainey & Best (project manager/QS); HD Design (architects) and BCD Partnership (structural & civil engineers).